Monitor — Ongoing Works
Rollup last refreshed: 2026-08-31 07:04:14.40539
Works ongoing
10,787
Sanctioned (pure scheme)
₹164.55 Cr
Expenditure since inception
₹62.39 Cr
Balance cost (unspent)
₹102.16 Cr
Wage ₹61.75 Cr · Material ₹40.41 Cr
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,640 works
₹76.33 Cr sanctioned
₹26.94 Cr spent (35%)
02
Construction of Well
689 works
₹21.85 Cr sanctioned
₹9.96 Cr spent (46%)
03
Rural Housing
7,406 works
₹19.99 Cr sanctioned
₹8.72 Cr spent (44%)
04
Farm Pond
307 works
₹10.87 Cr sanctioned
₹2.65 Cr spent (24%)
05
Construction of Tank
66 works
₹7.67 Cr sanctioned
₹2.85 Cr spent (37%)
06
Construction of Road and Culvert
61 works
₹6.68 Cr sanctioned
₹3.91 Cr spent (59%)
07
Construction of Percolation Tank
56 works
₹2.76 Cr sanctioned
₹40.64 L spent (15%)
08
Cattle Shed
61 works
₹2.20 Cr sanctioned
₹1.85 Cr spent (84%)
09
Constr of GP Bhawan
24 works
₹2.17 Cr sanctioned
₹1.55 Cr spent (71%)
10
Construction of Trench
31 works
₹1.98 Cr sanctioned
₹23.19 L spent (12%)