Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 06:53:12.593559
Works ongoing
20,016
Sanctioned (pure scheme)
₹354.15 Cr
Expenditure since inception
₹4.46 Cr
Balance cost (unspent)
₹349.69 Cr
Wage ₹191.34 Cr · Material ₹158.34 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
30-Jul
13-Aug
27-Aug
10-Sep
24-Sep
08-Oct
Lowest mandays this fortnight — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
2,797 works
₹96.23 Cr sanctioned
₹15.11 L spent (0%)
02
Construction of Tank
224 works
₹42.12 Cr sanctioned
₹54.14 L spent (1%)
03
Plantation
1,629 works
₹39.07 Cr sanctioned
₹35.20 L spent (1%)
04
Rural Housing
12,407 works
₹33.50 Cr sanctioned
₹3.07 Cr spent (9%)
05
Construction of Check Dam/Stop Dam
236 works
₹32.45 Cr sanctioned
₹7.01 L spent (0%)
06
Construction of Percolation Tank
211 works
₹29.66 Cr sanctioned
₹4.35 L spent (0%)
07
Construction of Road and Culvert
108 works
₹16.95 Cr sanctioned
₹1.06 L spent (0%)
08
Farm Pond
660 works
₹16.21 Cr sanctioned
₹10.25 L spent (1%)
09
Well Recharge
544 works
₹10.40 Cr sanctioned
₹4.95 L spent (0%)
10
Cattle Shed
417 works
₹6.36 Cr sanctioned
₹9,600 spent (0%)