Monitor — Ongoing Works
Rollup last refreshed: 2026-09-11 07:02:56.605851
Works ongoing
20,510
Sanctioned (pure scheme)
₹357.04 Cr
Expenditure since inception
₹1.68 Cr
Balance cost (unspent)
₹355.36 Cr
Wage ₹196.00 Cr · Material ₹159.36 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
2,812 works
₹96.69 Cr sanctioned
₹6.45 L spent (0%)
02
Construction of Tank
226 works
₹42.36 Cr sanctioned
₹32.20 L spent (1%)
03
Plantation
1,629 works
₹39.08 Cr sanctioned
₹12.56 L spent (0%)
04
Rural Housing
12,853 works
₹34.70 Cr sanctioned
₹99.01 L spent (3%)
05
Construction of Check Dam/Stop Dam
242 works
₹32.63 Cr sanctioned
₹3.59 L spent (0%)
06
Construction of Percolation Tank
212 works
₹29.91 Cr sanctioned
₹1.91 L spent (0%)
07
Construction of Road and Culvert
108 works
₹16.95 Cr sanctioned
₹51,810 spent (0%)
08
Farm Pond
661 works
₹16.22 Cr sanctioned
₹5.22 L spent (0%)
09
Well Recharge
555 works
₹10.43 Cr sanctioned
₹3.41 L spent (0%)
10
Cattle Shed
417 works
₹6.36 Cr sanctioned
₹5,400 spent (0%)