Monitor — Ongoing Works
Rollup last refreshed: 2026-09-21 06:52:32.583578
Works ongoing
23
Sanctioned (pure scheme)
₹51.76 L
Expenditure since inception
₹7.11 L
Balance cost (unspent)
₹44.65 L
Wage ₹32.07 L · Material ₹12.58 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
6 works
₹32.23 L sanctioned
₹2.20 L spent (7%)
02
Construction of Trench
2 works
₹9.02 L sanctioned
₹1.24 L spent (14%)
03
Constr of Compound wall
1 works
₹6.74 L sanctioned
₹3.60 L spent (53%)
04
Rural Housing
13 works
₹3.51 L sanctioned
₹8,400 spent (2%)
05
Construction of Recharge Pits
1 works
₹25,899 sanctioned
₹0 spent (0%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)