Monitor — Ongoing Works
Rollup last refreshed: 2026-09-11 07:02:56.605851
Works ongoing
133
Sanctioned (pure scheme)
₹2.11 Cr
Expenditure since inception
₹6.19 L
Balance cost (unspent)
₹2.05 Cr
Wage ₹1.10 Cr · Material ₹95.02 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
10 works
₹94.31 L sanctioned
₹63,000 spent (1%)
02
Constr of Aganwadi
1 works
₹38.05 L sanctioned
₹0 spent (0%)
03
Rural Housing
118 works
₹31.86 L sanctioned
₹2.56 L spent (8%)
04
Construction of Tank
2 works
₹27.41 L sanctioned
₹3.00 L spent (11%)
05
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹19.80 L sanctioned
₹0 spent (0%)
06
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)