Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
16
Sanctioned (pure scheme)
₹29.72 L
Expenditure since inception
₹14.97 L
Balance cost (unspent)
₹14.75 L
Wage ₹6.58 L · Material ₹8.16 L
Expenditure trend
−₹1.67 Cr
This Week
₹5.71 Cr
Last Week
▼ 129.3% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹1.22 Cr
Mandays trend
-99,460
This Week
-2,27,622
Last Week
▲ 56.3%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
5 works
₹16.93 L sanctioned
₹13.05 L spent (77%)
02
Plantation
2 works
₹8.20 L sanctioned
₹24,955 spent (3%)
03
Construction of Well
1 works
₹2.71 L sanctioned
₹28,710 spent (11%)
04
Rural Housing
8 works
₹1.88 L sanctioned
₹1.38 L spent (74%)
05
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 8 1.88 1.38 0.50
74%
2 Farm Pond 5 16.93 13.05 3.87
77%
3 Plantation 2 8.20 0.25 7.95
3%
4 Construction of Well 1 2.71 0.29 2.42
11%
Total 16 29.72 14.97 14.75