Monitor — Ongoing Works
Rollup last refreshed: 2026-09-06 06:52:15.262196
Works ongoing
24
Sanctioned (pure scheme)
₹39.13 L
Expenditure since inception
₹84,000
Balance cost (unspent)
₹38.29 L
Wage ₹18.80 L · Material ₹19.49 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
7 works
₹21.69 L sanctioned
₹0 spent (0%)
02
Plantation
5 works
₹14.20 L sanctioned
₹37,800 spent (3%)
03
Rural Housing
12 works
₹3.24 L sanctioned
₹46,200 spent (14%)
04
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)