Monitor — Ongoing Works
Rollup last refreshed: 2026-09-03 07:03:16.173614
Works ongoing
4,914
Sanctioned (pure scheme)
₹77.76 Cr
Expenditure since inception
₹22.79 Cr
Balance cost (unspent)
₹54.97 Cr
Wage ₹30.61 Cr · Material ₹24.35 Cr
Expenditure trend
Jun-26
Jul-26
Aug-26
Sep-26
Slowest spending this month — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,279 works
₹41.36 Cr sanctioned
₹10.02 Cr spent (24%)
02
Rural Housing
2,651 works
₹7.16 Cr sanctioned
₹3.75 Cr spent (52%)
03
Construction of Road and Culvert
46 works
₹6.78 Cr sanctioned
₹3.26 Cr spent (48%)
04
Farm Pond
134 works
₹3.84 Cr sanctioned
₹1.42 Cr spent (37%)
05
Cattle Shed
73 works
₹2.98 Cr sanctioned
₹82.97 L spent (28%)
06
Construction of Check Dam/Stop Dam
31 works
₹1.91 Cr sanctioned
₹22.87 L spent (12%)
07
Construction of Well
50 works
₹1.41 Cr sanctioned
₹52.56 L spent (37%)
08
Constr of Aganwadi
24 works
₹1.21 Cr sanctioned
₹36.89 L spent (31%)
09
Construction of Tank
17 works
₹1.14 Cr sanctioned
₹16.82 L spent (15%)
10
Solid and Liquid Waste Management
94 works
₹1.06 Cr sanctioned
₹19.64 L spent (19%)