Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 06:51:54.449291
Works ongoing
24
Sanctioned (pure scheme)
₹42.86 L
Expenditure since inception
₹1.64 L
Balance cost (unspent)
₹41.22 L
Wage ₹21.99 L · Material ₹19.23 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
4 works
₹20.23 L sanctioned
₹0 spent (0%)
02
Construction of Well
5 works
₹17.97 L sanctioned
₹0 spent (0%)
03
Rural Housing
13 works
₹3.51 L sanctioned
₹1.43 L spent (41%)
04
Community Sanitary Complex
1 works
₹80,000 sanctioned
₹0 spent (0%)
05
Constr of Cement Concrete Roads
1 works
₹35,000 sanctioned
₹21,600 spent (62%)
06
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)