Monitor — Ongoing Works
Rollup last refreshed: 2026-10-28 06:52:51.948451
Works ongoing
113
Sanctioned (pure scheme)
₹58.95 L
Expenditure since inception
₹11.34 L
Balance cost (unspent)
₹47.61 L
Wage ₹28.55 L · Material ₹19.06 L
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
11 works
₹29.63 L sanctioned
₹58,800 spent (2%)
02
Rural Housing
99 works
₹26.73 L sanctioned
₹10.74 L spent (40%)
03
Constr of Gabion
1 works
₹1.58 L sanctioned
₹300 spent (0%)
04
Construction of Check Dam/Stop Dam
1 works
₹70,699 sanctioned
₹300 spent (0%)
05
Roof Water Harvesting on gov/panchayat bldg
1 works
₹30,497 sanctioned
₹600 spent (2%)
06
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)