Monitor — Ongoing Works
Rollup last refreshed: 2026-10-28 07:05:36.406139
Works ongoing
17,347
Sanctioned (pure scheme)
₹163.88 Cr
Expenditure since inception
₹62.34 Cr
Balance cost (unspent)
₹101.54 Cr
Wage ₹56.87 Cr · Material ₹44.67 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
Jun-26
Jul-26
Aug-26
Sep-26
Oct-26
Lowest mandays this month — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,463 works
₹37.14 Cr sanctioned
₹10.83 Cr spent (29%)
02
Rural Housing
13,200 works
₹35.61 Cr sanctioned
₹17.11 Cr spent (48%)
03
Construction of Well
742 works
₹22.69 Cr sanctioned
₹10.70 Cr spent (47%)
04
Construction of Road and Culvert
106 works
₹16.39 Cr sanctioned
₹8.45 Cr spent (52%)
05
Farm Pond
238 works
₹8.15 Cr sanctioned
₹2.57 Cr spent (32%)
06
Construction of Tank
104 works
₹6.24 Cr sanctioned
₹1.40 Cr spent (22%)
07
Cattle Shed
95 works
₹5.84 Cr sanctioned
₹2.79 Cr spent (48%)
08
Construction of Check Dam/Stop Dam
53 works
₹4.20 Cr sanctioned
₹57.57 L spent (14%)
09
Well Recharge
123 works
₹3.95 Cr sanctioned
₹97.75 L spent (25%)
10
Constr of Cement Concrete Roads
323 works
₹2.92 Cr sanctioned
₹1.25 Cr spent (43%)