Monitor — Ongoing Works
Rollup last refreshed: 2026-10-26 10:02:28.474231
Works ongoing
17,428
Sanctioned (pure scheme)
₹164.62 Cr
Expenditure since inception
₹62.23 Cr
Balance cost (unspent)
₹102.39 Cr
Wage ₹57.70 Cr · Material ₹44.69 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
- SINGRAULI — CHITRANGI-856
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,465 works
₹37.17 Cr sanctioned
₹10.83 Cr spent (29%)
02
Rural Housing
13,263 works
₹35.78 Cr sanctioned
₹16.60 Cr spent (46%)
03
Construction of Well
746 works
₹22.81 Cr sanctioned
₹10.80 Cr spent (47%)
04
Construction of Road and Culvert
108 works
₹16.66 Cr sanctioned
₹8.69 Cr spent (52%)
05
Farm Pond
242 works
₹8.26 Cr sanctioned
₹2.62 Cr spent (32%)
06
Construction of Tank
104 works
₹6.24 Cr sanctioned
₹1.40 Cr spent (22%)
07
Cattle Shed
95 works
₹5.84 Cr sanctioned
₹2.79 Cr spent (48%)
08
Construction of Check Dam/Stop Dam
53 works
₹4.20 Cr sanctioned
₹57.01 L spent (14%)
09
Well Recharge
123 works
₹3.95 Cr sanctioned
₹97.75 L spent (25%)
10
Constr of Cement Concrete Roads
325 works
₹2.94 Cr sanctioned
₹1.25 Cr spent (43%)