Monitor — Ongoing Works
Rollup last refreshed: 2026-08-20 07:27:54.710413
Works ongoing
15,382
Sanctioned (pure scheme)
₹98.32 Cr
Expenditure since inception
₹42.25 Cr
Balance cost (unspent)
₹56.07 Cr
Wage ₹36.15 Cr · Material ₹19.92 Cr
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
12,803 works
₹30.05 Cr sanctioned
₹13.90 Cr spent (46%)
02
Plantation
1,393 works
₹27.32 Cr sanctioned
₹9.35 Cr spent (34%)
03
Construction of Well
269 works
₹7.60 Cr sanctioned
₹3.53 Cr spent (46%)
04
Construction of Check Dam/Stop Dam
53 works
₹5.02 Cr sanctioned
₹3.19 Cr spent (64%)
05
Construction of Road and Culvert
36 works
₹4.29 Cr sanctioned
₹1.99 Cr spent (46%)
06
Construction of Tank
40 works
₹3.79 Cr sanctioned
₹1.87 Cr spent (49%)
07
Farm Pond
103 works
₹2.94 Cr sanctioned
₹59.11 L spent (20%)
08
Cattle Shed
22 works
₹2.57 Cr sanctioned
₹1.65 Cr spent (64%)
09
Constr of GP Bhawan
29 works
₹2.22 Cr sanctioned
₹1.05 Cr spent (47%)
10
Constr of Cement Concrete Roads
177 works
₹2.19 Cr sanctioned
₹85.98 L spent (39%)