Works ongoing
13,168
Sanctioned (pure scheme)
₹152.01 Cr
Expenditure since inception
₹4.86 Cr
Balance cost (unspent)
₹147.15 Cr
Wage ₹85.27 Cr · Material ₹61.88 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,425 works
₹44.09 Cr sanctioned
₹63.43 L spent (1%)
02
Rural Housing
9,721 works
₹26.24 Cr sanctioned
₹3.49 Cr spent (13%)
03
Construction of Road and Culvert
94 works
₹13.73 Cr sanctioned
₹7.45 L spent (1%)
04
Cattle Shed
51 works
₹7.08 Cr sanctioned
₹10,466 spent (0%)
05
Construction of Tank
68 works
₹7.02 Cr sanctioned
₹15.74 L spent (2%)
06
Construction of Check Dam/Stop Dam
92 works
₹5.79 Cr sanctioned
₹11.37 L spent (2%)
07
Farm Pond
165 works
₹5.53 Cr sanctioned
₹32,038 spent (0%)
08
Construction of Trench
74 works
₹4.34 Cr sanctioned
₹25.13 L spent (6%)
09
Construction of Well
143 works
₹4.34 Cr sanctioned
₹4.24 L spent (1%)
10
Construction of Bund
68 works
₹3.69 Cr sanctioned
₹0 spent (0%)