Monitor — Ongoing Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
Reset filters
Works ongoing
30
Sanctioned (pure scheme)
₹23.23 L
Expenditure since inception
₹6.56 L
Balance cost (unspent)
₹16.67 L
Wage ₹8.23 L · Material ₹8.44 L
Expenditure trend
−₹1.39 L
This Week
−₹20.03 L
Last Week
▲ 93.1% vs last week
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
  • DHAR — UMARBAN−₹79,542
Mandays trend
-598
This Week
-34,371
Last Week
▲ 98.3%
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
  • DHAR — UMARBAN-598

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
3 works
₹6.46 L sanctioned
₹41,819 spent (6%)
02
Construction of Road and Culvert
1 works
₹5.51 L sanctioned
₹2.82 L spent (51%)
03
Land Development
1 works
₹3.77 L sanctioned
₹16,838 spent (4%)
04
Rural Housing
15 works
₹3.52 L sanctioned
₹2.41 L spent (68%)
05
Construction of Crematorium
1 works
₹2.31 L sanctioned
₹11,079 spent (5%)
06
Solid and Liquid Waste Management
3 works
₹1.17 L sanctioned
₹56,291 spent (48%)
07
Repair & Maint of Community infrastructure
5 works
₹43,900 sanctioned
₹2,110 spent (5%)
08
Construction of NADEP/Vermi Compost Pit
1 works
₹5,800 sanctioned
₹5,256 spent (91%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 15 3.52 2.41 1.12
68%
2 Repair & Maint of Community infrastructure 5 0.44 0.02 0.42
5%
3 Solid and Liquid Waste Management 3 1.17 0.56 0.61
48%
4 Plantation 3 6.46 0.42 6.04
7%
5 Land Development 1 3.77 0.17 3.60
5%
6 Construction of Crematorium 1 2.31 0.11 2.20
5%
7 Construction of NADEP/Vermi Compost Pit 1 0.06 0.05 0.01
91%
8 Construction of Road and Culvert 1 5.51 2.82 2.69
51%
Total 30 23.23 6.56 16.67
All 8 rows (zero-value rows hidden) ⇩ Export to Excel