Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
18
Sanctioned (pure scheme)
₹57.40 L
Expenditure since inception
₹27.36 L
Balance cost (unspent)
₹30.04 L
Wage ₹14.36 L · Material ₹15.67 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹25.06 L sanctioned
₹17.49 L spent (70%)
02
Plantation
6 works
₹22.28 L sanctioned
₹5.52 L spent (25%)
03
Construction of Well
1 works
₹5.06 L sanctioned
₹2.87 L spent (57%)
04
Well Recharge
1 works
₹3.39 L sanctioned
₹91,945 spent (27%)
05
Rural Housing
6 works
₹1.41 L sanctioned
₹56,292 spent (40%)
06
Constr of Kitchen Shed
3 works
₹19,400 sanctioned
₹400 spent (2%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)