Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Works ongoing
13,268
Sanctioned (pure scheme)
₹152.20 Cr
Expenditure since inception
₹55.35 Cr
Balance cost (unspent)
₹96.85 Cr
Wage ₹55.60 Cr · Material ₹41.26 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,425 works
₹44.09 Cr sanctioned
₹10.22 Cr spent (23%)
02
Rural Housing
9,823 works
₹26.52 Cr sanctioned
₹11.46 Cr spent (43%)
03
Construction of Road and Culvert
94 works
₹13.73 Cr sanctioned
₹7.31 Cr spent (53%)
04
Cattle Shed
51 works
₹7.08 Cr sanctioned
₹5.17 Cr spent (73%)
05
Construction of Tank
68 works
₹7.02 Cr sanctioned
₹2.45 Cr spent (35%)
06
Construction of Check Dam/Stop Dam
92 works
₹5.79 Cr sanctioned
₹1.18 Cr spent (20%)
07
Farm Pond
165 works
₹5.53 Cr sanctioned
₹87.22 L spent (16%)
08
Construction of Well
143 works
₹4.34 Cr sanctioned
₹1.75 Cr spent (40%)
09
Construction of Trench
72 works
₹4.25 Cr sanctioned
₹1.24 Cr spent (29%)
10
Construction of Bund
68 works
₹3.69 Cr sanctioned
₹69.75 L spent (19%)