Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
27
Sanctioned (pure scheme)
₹1.63 Cr
Expenditure since inception
₹1.13 Cr
Balance cost (unspent)
₹50.62 L
Wage ₹29.58 L · Material ₹21.04 L
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
6 works
₹1.17 Cr sanctioned
₹87.52 L spent (75%)
02
Constr of Cement Concrete Roads
1 works
₹13.67 L sanctioned
₹11.26 L spent (82%)
03
Construction of Well
4 works
₹12.90 L sanctioned
₹9.39 L spent (73%)
04
Plantation
10 works
₹8.00 L sanctioned
₹2.34 L spent (29%)
05
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹15,054 spent (3%)
06
Well Recharge
1 works
₹4.51 L sanctioned
₹1.36 L spent (30%)
07
Construction of NADEP/Vermi Compost Pit
2 works
₹1.93 L sanctioned
₹40,104 spent (21%)
08
Rural Housing
1 works
₹28,500 sanctioned
₹22,446 spent (79%)
09
Constr of Kitchen Shed
1 works
₹16,093 sanctioned
₹2,316 spent (14%)
10
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
0 works
₹0 sanctioned
₹0 spent (0%)