Monitor — Ongoing Works
Rollup last refreshed: 2026-09-16 08:34:45.218851
Works ongoing
36
Sanctioned (pure scheme)
₹1.70 Cr
Expenditure since inception
₹1.18 Cr
Balance cost (unspent)
₹52.47 L
Wage ₹31.75 L · Material ₹20.72 L
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- SHAHDOL — GOHPARU−₹38.03 L
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
6 works
₹1.17 Cr sanctioned
₹86.88 L spent (74%)
02
Construction of Well
5 works
₹15.73 L sanctioned
₹11.69 L spent (74%)
03
Constr of Cement Concrete Roads
1 works
₹13.67 L sanctioned
₹11.26 L spent (82%)
04
Plantation
10 works
₹8.00 L sanctioned
₹1.13 L spent (14%)
05
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹15,054 spent (3%)
06
Well Recharge
1 works
₹4.51 L sanctioned
₹1.36 L spent (30%)
07
Farm Pond
2 works
₹4.38 L sanctioned
₹3.81 L spent (87%)
08
Rural Housing
6 works
₹1.49 L sanctioned
₹1.33 L spent (89%)
09
Construction of Recharge Pits
2 works
₹51,799 sanctioned
₹30,975 spent (60%)
10
Constr of Kitchen Shed
1 works
₹16,093 sanctioned
₹2,316 spent (14%)