Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:57:48.415109
Works ongoing
15
Sanctioned (pure scheme)
₹1.09 Cr
Expenditure since inception
₹79.07 L
Balance cost (unspent)
₹30.40 L
Wage ₹6.06 L · Material ₹24.34 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
1 works
₹59.01 L sanctioned
₹45.97 L spent (78%)
02
Construction of Tank
2 works
₹29.08 L sanctioned
₹26.55 L spent (91%)
03
Constr of Cement Concrete Roads
1 works
₹11.54 L sanctioned
₹1.69 L spent (15%)
04
Construction of Check Dam/Stop Dam
1 works
₹4.00 L sanctioned
₹2.51 L spent (63%)
05
Farm Pond
1 works
₹3.27 L sanctioned
₹1.26 L spent (39%)
06
Rural Housing
9 works
₹2.57 L sanctioned
₹1.08 L spent (42%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)