Monitor — Ongoing Works
Rollup last refreshed: 2026-09-04 07:04:21.536086
Works ongoing
12
Sanctioned (pure scheme)
₹94.81 L
Expenditure since inception
₹57.53 L
Balance cost (unspent)
₹37.28 L
Wage ₹24.06 L · Material ₹13.22 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹48.82 L sanctioned
₹45.45 L spent (93%)
02
Plantation
5 works
₹31.84 L sanctioned
₹7.28 L spent (23%)
03
Construction of Trench
2 works
₹9.12 L sanctioned
₹1.79 L spent (20%)
04
Construction of Well
1 works
₹2.46 L sanctioned
₹1.30 L spent (53%)
05
Farm Pond
1 works
₹2.00 L sanctioned
₹1.30 L spent (65%)
06
Rural Housing
2 works
₹57,000 sanctioned
₹41,328 spent (73%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)