MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-23 10:33:29.479603
to
Reset filters
Works ongoing
7,194
Sanctioned (pure scheme)
₹114.03 Cr
Expenditure since inception
₹3.65 Cr
Balance cost (unspent)
₹110.38 Cr
Wage ₹52.83 Cr · Material ₹57.56 Cr
Expenditure trend
₹34.15 Cr
This Week
₹83.39 Cr
Last Week
▼ 59.1% vs last week
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
  • KATNI — BADWARA−₹27.11 L
Mandays trend
8,03,111
This Week
12,00,800
Last Week
▼ 33.1%
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
  • BETUL — GHORA DONGRI0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,860 works
₹43.20 Cr sanctioned
₹79.41 L spent (2%)
02
Construction of Road and Culvert
109 works
₹14.24 Cr sanctioned
₹9.91 L spent (1%)
03
Rural Housing
4,212 works
₹12.01 Cr sanctioned
₹2.07 Cr spent (17%)
04
Culvert
47 works
₹7.23 Cr sanctioned
₹0 spent (0%)
05
Constr of Food Grain storage
43 works
₹6.02 Cr sanctioned
₹10.70 L spent (2%)
06
Construction of Tank
42 works
₹5.43 Cr sanctioned
₹8.61 L spent (2%)
07
Construction of Check Dam/Stop Dam
49 works
₹4.68 Cr sanctioned
₹3.03 L spent (1%)
08
Constr of Cement Concrete Roads
150 works
₹4.36 Cr sanctioned
₹1.51 L spent (0%)
09
Construction of Well
123 works
₹3.10 Cr sanctioned
₹1.20 L spent (0%)
10
Farm Pond
93 works
₹2.42 Cr sanctioned
₹57,087 spent (0%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 4,212 12.01 2.07 9.94
17%
2 Plantation 1,860 43.20 0.79 42.41
2%
3 Constr of Cement Concrete Roads 150 4.36 0.02 4.34
0%
4 Construction of Well 123 3.10 0.01 3.09
0%
5 Solid and Liquid Waste Management 112 0.61 0.01 0.60
1%
6 Construction of Road and Culvert 109 14.24 0.10 14.14
1%
7 Farm Pond 93 2.42 0.01 2.41
0%
8 Roof Water Harvesting on gov/panchayat bldg 50 0.17 0.01 0.16
6%
9 Construction of Check Dam/Stop Dam 49 4.68 0.03 4.65
1%
10 Culvert 47 7.23 0.00 7.23
0%
11 Constr of Food Grain storage 43 6.02 0.11 5.91
2%
12 Construction of Tank 42 5.43 0.09 5.35
2%
13 Construction of NADEP/Vermi Compost Pit 38 0.32 0.00 0.32
0%
14 Construction of Trench 36 0.94 0.35 0.59
38%
15 Cattle Shed 27 0.24 0.00 0.24
0%
16 Community Sanitary Complex 25 1.29 0.00 1.29
0%
17 Well Recharge 15 0.23 0.00 0.23
1%
18 (uncategorised) 12 1.53 0.00 1.53
0%
19 Construction of Recharge Pits 12 0.03 0.00 0.03
3%
20 Construction of Fish Drying Infrastructure 12 0.14 0.00 0.14
0%
21 Construction of Toilets 11 0.02 0.00 0.02
0%
22 Constr of Aganwadi 10 0.47 0.02 0.45
4%
23 Construction of Bund 10 0.50 0.00 0.50
0%
24 Constr of GP Bhawan 10 0.61 0.00 0.61
0%
25 Other Works 8 0.11 0.00 0.11
0%
26 Land Development 8 0.25 0.00 0.25
0%
27 Construction of building/workshed for SHG 7 0.40 0.00 0.40
0%
28 Nursery Development 7 0.97 0.01 0.96
1%
29 Goat Shelter 6 0.04 0.00 0.04
0%
30 Works for Flood Control and Protection 6 0.23 0.00 0.23
0%
31 Constr of Kitchen Shed 5 0.17 0.00 0.17
0%
32 Constr of Compound wall 4 0.19 0.00 0.19
0%
33 Terracing 4 0.20 0.00 0.20
0%
34 Poultry Shelter 4 0.06 0.00 0.06
0%
35 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 3 0.33 0.00 0.33
0%
36 Construction of Play field 3 0.24 0.00 0.24
0%
37 Repair & maint of Road 3 0.05 0.00 0.05
0%
38 Repair & maint of Pond/ Tank 3 0.15 0.00 0.15
0%
39 Construction of Percolation Tank 3 0.16 0.00 0.16
0%
40 Constr of Gabion 2 0.12 0.00 0.12
4%
41 Construction of Spur 2 0.20 0.02 0.19
9%
42 Construction of Crematorium 1 0.03 0.00 0.03
0%
43 Deepening / Desilting of Flood Channels 1 0.00 0.00 0.00
0%
44 Construction of Village Haats 1 0.20 0.00 0.20
0%
45 Repair & maint of Percolation Tank 1 0.04 0.00 0.04
0%
46 Repaire and Maint of NADEP/Vermi Compost Pit 1 0.00 0.00 0.00
0%
47 Bio-Fertilizer 1 0.06 0.00 0.06
0%
48 Bio-gas plant 1 0.01 0.00 0.01
0%
49 Construction of Canal 1 0.05 0.00 0.05
0%
Total 7,194 114.03 3.65 110.38
All 49 rows (zero-value rows hidden) ⇩ Export to Excel