Monitor — Ongoing Works
Rollup last refreshed: 2026-10-04 07:04:00.535302
Works ongoing
11,994
Sanctioned (pure scheme)
₹181.59 Cr
Expenditure since inception
₹82.22 Cr
Balance cost (unspent)
₹99.37 Cr
Wage ₹63.08 Cr · Material ₹36.30 Cr
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
351 works
₹48.80 Cr sanctioned
₹24.03 Cr spent (49%)
02
Plantation
595 works
₹32.14 Cr sanctioned
₹14.01 Cr spent (44%)
03
Rural Housing
10,072 works
₹27.47 Cr sanctioned
₹10.50 Cr spent (38%)
04
Construction of Check Dam/Stop Dam
144 works
₹18.75 Cr sanctioned
₹7.47 Cr spent (40%)
05
Constr of Cement Concrete Roads
127 works
₹10.17 Cr sanctioned
₹7.87 Cr spent (77%)
06
Construction of Road and Culvert
55 works
₹7.72 Cr sanctioned
₹5.43 Cr spent (70%)
07
Construction of Bund
52 works
₹4.73 Cr sanctioned
₹26.44 L spent (6%)
08
Farm Pond
125 works
₹4.52 Cr sanctioned
₹84.79 L spent (19%)
09
Works for Flood Control and Protection
31 works
₹3.55 Cr sanctioned
₹1.83 Cr spent (52%)
10
Constr of GP Bhawan
26 works
₹3.16 Cr sanctioned
₹1.06 Cr spent (34%)