| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Farm Pond | 15 | 14.56 | 0.00 | 14.56 | 0% |
| 2 | Cattle Shed | 3 | 3.36 | 0.00 | 3.36 | 0% |
| 3 | Construction of Well | 3 | 4.10 | 0.26 | 3.84 | 6% |
| 4 | Construction of Tank | 2 | 15.97 | 0.00 | 15.97 | 0% |
| 5 | Well Recharge | 2 | 2.67 | 0.00 | 2.67 | 0% |
| 6 | Other Works | 1 | 1.03 | 0.00 | 1.03 | 0% |
| 7 | Plantation | 1 | 1.41 | 0.16 | 1.25 | 11% |
| 8 | Construction of Check Dam/Stop Dam | 1 | 14.67 | 0.00 | 14.67 | 0% |
| 9 | Constr of GP Bhawan | 1 | 0.75 | 0.00 | 0.75 | 0% |
| 10 | Construction of Percolation Tank | 1 | 0.93 | 0.00 | 0.93 | 0% |
| Total | 30 | 59.46 | 0.42 | 59.04 |