Works ongoing
57
Sanctioned (pure scheme)
₹95.77 L
Expenditure since inception
₹40.05 L
Balance cost (unspent)
₹55.71 L
Wage ₹34.16 L · Material ₹21.55 L
Expenditure trend
₹23.77 Cr
This Week
₹39.19 Cr
Last Week
▼ 39.4% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • RAJGARH — SARANGPUR−₹1.04 Cr
Mandays trend
7,49,397
This Week
10,41,857
Last Week
▼ 28.1%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-16,931

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
9 works
₹26.91 L sanctioned
₹11.11 L spent (41%)
02
Plantation
5 works
₹16.22 L sanctioned
₹3.97 L spent (24%)
03
Well Recharge
19 works
₹16.00 L sanctioned
₹6.00 L spent (38%)
04
Construction of Check Dam/Stop Dam
1 works
₹13.95 L sanctioned
₹5.37 L spent (38%)
05
Farm Pond
4 works
₹8.02 L sanctioned
₹4.71 L spent (59%)
06
Construction of Well
2 works
₹4.51 L sanctioned
₹1.93 L spent (43%)
07
Rural Housing
11 works
₹3.14 L sanctioned
₹2.44 L spent (78%)
08
Cattle Shed
2 works
₹2.04 L sanctioned
₹1.46 L spent (72%)
09
Culvert
1 works
₹1.55 L sanctioned
₹83,716 spent (54%)
10
Construction of Percolation Tank
1 works
₹1.50 L sanctioned
₹87,644 spent (58%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Well Recharge 19 16.00 6.00 9.99
38%
2 Rural Housing 11 3.14 2.44 0.70
78%
3 Construction of Bund 9 26.91 11.11 15.80
41%
4 Plantation 5 16.22 3.97 12.26
25%
5 Farm Pond 4 8.02 4.71 3.32
59%
6 Construction of Well 2 4.51 1.93 2.58
43%
7 Cattle Shed 2 2.04 1.46 0.58
72%
8 Construction of Percolation Tank 1 1.50 0.88 0.62
59%
9 Culvert 1 1.55 0.84 0.71
54%
10 Terracing 1 1.49 1.06 0.43
71%
11 Construction of Check Dam/Stop Dam 1 13.95 5.37 8.59
39%
12 Community Sanitary Complex 1 0.43 0.29 0.14
69%
Total 57 95.77 40.05 55.71