Monitor — Ongoing Works
Rollup last refreshed: 2026-09-10 07:02:43.339169
Works ongoing
25
Sanctioned (pure scheme)
₹33.50 L
Expenditure since inception
₹22.39 L
Balance cost (unspent)
₹11.11 L
Wage ₹5.93 L · Material ₹5.19 L
Expenditure trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
- SHAJAPUR — MOMAN BADODIYA−₹26.22 L
Mandays trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹18.58 L sanctioned
₹15.22 L spent (82%)
02
Rural Housing
17 works
₹4.77 L sanctioned
₹2.85 L spent (60%)
03
Boulder Check/Gully Plug
2 works
₹3.42 L sanctioned
₹1.32 L spent (39%)
04
Well Recharge
1 works
₹3.32 L sanctioned
₹68,695 spent (21%)
05
Cattle Shed
2 works
₹1.66 L sanctioned
₹1.45 L spent (87%)
06
Constr of Gabion
1 works
₹1.10 L sanctioned
₹27,540 spent (25%)
07
Constr of Aganwadi
1 works
₹66,000 sanctioned
₹59,401 spent (90%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)