Monitor — Ongoing Works
Rollup last refreshed: 2026-09-07 06:52:02.404114
Works ongoing
14,932
Sanctioned (pure scheme)
₹123.06 Cr
Expenditure since inception
₹3.02 Cr
Balance cost (unspent)
₹120.04 Cr
Wage ₹75.68 Cr · Material ₹44.37 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,163 works
₹34.78 Cr sanctioned
₹17.31 L spent (0%)
02
Rural Housing
11,720 works
₹31.64 Cr sanctioned
₹1.46 Cr spent (5%)
03
Construction of Well
840 works
₹20.93 Cr sanctioned
₹4.90 L spent (0%)
04
Construction of Check Dam/Stop Dam
131 works
₹6.01 Cr sanctioned
₹9.49 L spent (2%)
05
Cattle Shed
238 works
₹5.62 Cr sanctioned
₹83.53 L spent (15%)
06
Construction of Trench
116 works
₹4.67 Cr sanctioned
₹21.80 L spent (5%)
07
Farm Pond
116 works
₹2.75 Cr sanctioned
₹20,600 spent (0%)
08
Construction of Tank
55 works
₹2.32 Cr sanctioned
₹10.20 L spent (4%)
09
Construction of Percolation Tank
20 works
₹1.76 Cr sanctioned
₹5.23 L spent (3%)
10
Construction of Road and Culvert
16 works
₹1.69 Cr sanctioned
₹0 spent (0%)