Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
16,412
Sanctioned (pure scheme)
₹124.08 Cr
Expenditure since inception
₹57.86 Cr
Balance cost (unspent)
₹66.22 Cr
Wage ₹36.37 Cr · Material ₹29.85 Cr
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,187 works
₹35.41 Cr sanctioned
₹18.06 Cr spent (51%)
02
Rural Housing
13,098 works
₹30.75 Cr sanctioned
₹17.79 Cr spent (58%)
03
Construction of Well
887 works
₹22.03 Cr sanctioned
₹10.73 Cr spent (49%)
04
Construction of Check Dam/Stop Dam
132 works
₹5.99 Cr sanctioned
₹1.32 Cr spent (22%)
05
Cattle Shed
236 works
₹5.58 Cr sanctioned
₹2.83 Cr spent (51%)
06
Construction of Trench
88 works
₹3.74 Cr sanctioned
₹61.65 L spent (16%)
07
Farm Pond
125 works
₹2.92 Cr sanctioned
₹52.54 L spent (18%)
08
Construction of Tank
55 works
₹2.30 Cr sanctioned
₹70.12 L spent (30%)
09
Construction of Percolation Tank
22 works
₹1.83 Cr sanctioned
₹27.58 L spent (15%)
10
Construction of Road and Culvert
16 works
₹1.69 Cr sanctioned
₹83.64 L spent (49%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 13,098 30.75 17.79 12.96
58%
2 Plantation 1,187 35.41 18.06 17.35
51%
3 Construction of Well 887 22.03 10.73 11.30
49%
4 Cattle Shed 236 5.58 2.83 2.75
51%
5 Construction of Check Dam/Stop Dam 132 5.99 1.32 4.67
22%
6 Farm Pond 125 2.92 0.53 2.40
18%
7 Construction of Trench 88 3.74 0.62 3.13
17%
8 Constr of Cement Concrete Roads 83 1.09 0.62 0.47
57%
9 Construction of NADEP/Vermi Compost Pit 82 0.22 0.05 0.17
23%
10 Repair & maint of Water Harvesting Structures 62 0.50 0.06 0.44
12%
11 Construction of Tank 55 2.30 0.70 1.60
31%
12 Boulder Check/Gully Plug 45 1.59 0.38 1.22
24%
13 Well Recharge 33 1.16 0.29 0.87
25%
14 Constr of Aganwadi 28 1.08 0.39 0.69
36%
15 Terracing 26 0.83 0.15 0.68
18%
16 Construction of Percolation Tank 22 1.83 0.28 1.55
15%
17 Constr of Gabion 21 0.22 0.06 0.15
29%
18 Goat Shelter 18 0.14 0.04 0.09
32%
19 Construction of Road and Culvert 16 1.69 0.84 0.85
50%
20 Construction of Recharge Pits 16 0.22 0.04 0.18
18%
21 Repair & maint of Pond/ Tank 15 0.30 0.06 0.24
20%
22 Other Works 15 0.20 0.10 0.10
51%
23 Constr of GP Bhawan 12 1.54 0.99 0.55
64%
24 Community Sanitary Complex 11 0.05 0.03 0.02
54%
25 Repair & maint of Percolation Tank 11 0.15 0.02 0.13
11%
26 Repair & Maint of Check Dam/Stop Dam 11 0.20 0.03 0.17
14%
27 Roof Water Harvesting on gov/panchayat bldg 10 0.29 0.19 0.10
65%
28 Construction of building/workshed for SHG 10 0.34 0.14 0.20
40%
29 Solid and Liquid Waste Management 9 0.17 0.04 0.13
22%
30 Works for Flood Control and Protection 8 0.24 0.19 0.04
82%
31 Poultry Shelter 7 0.06 0.01 0.05
22%
32 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 7 0.15 0.01 0.14
6%
33 Construction of Play field 5 0.15 0.08 0.07
52%
34 Construction of Toilets 4 0.13 0.01 0.12
7%
35 Construction of Crematorium 4 0.12 0.08 0.04
66%
36 Land Development 4 0.18 0.04 0.14
23%
37 Constr of Compound wall 4 0.45 0.06 0.39
14%
38 Nursery Development 2 0.05 0.02 0.03
41%
39 Culvert 1 0.01 0.00 0.00
46%
40 Constr of Kitchen Shed 1 0.00 0.00 0.00
15%
41 Construction of Spur 1 0.01 0.00 0.01
25%
Total 16,412 124.08 57.86 66.22
All 41 rows (zero-value rows hidden) ⇩ Export to Excel