Monitor — Ongoing Works
Rollup last refreshed: 2026-08-28 07:07:21.360911
Works ongoing
3,821
Sanctioned (pure scheme)
₹101.52 Cr
Expenditure since inception
₹34.18 Cr
Balance cost (unspent)
₹67.34 Cr
Wage ₹35.82 Cr · Material ₹31.52 Cr
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
835 works
₹25.45 Cr sanctioned
₹3.99 Cr spent (16%)
02
Construction of Trench
277 works
₹9.58 Cr sanctioned
₹1.70 Cr spent (18%)
03
Construction of Road and Culvert
39 works
₹8.72 Cr sanctioned
₹4.23 Cr spent (49%)
04
Construction of Tank
46 works
₹5.87 Cr sanctioned
₹2.53 Cr spent (43%)
05
Farm Pond
227 works
₹5.85 Cr sanctioned
₹1.22 Cr spent (21%)
06
Constr of Cement Concrete Roads
68 works
₹5.57 Cr sanctioned
₹3.72 Cr spent (67%)
07
Construction of Well
107 works
₹3.35 Cr sanctioned
₹1.33 Cr spent (40%)
08
Rural Housing
1,350 works
₹3.17 Cr sanctioned
₹1.52 Cr spent (48%)
09
Construction of Check Dam/Stop Dam
27 works
₹3.13 Cr sanctioned
₹1.48 Cr spent (47%)
10
Constr of Aganwadi
59 works
₹3.00 Cr sanctioned
₹1.46 Cr spent (48%)