Monitor — Ongoing Works
Rollup last refreshed: 2026-10-27 06:52:31.645166
Works ongoing
5,932
Sanctioned (pure scheme)
₹202.63 Cr
Expenditure since inception
₹30.89 Cr
Balance cost (unspent)
₹171.74 Cr
Wage ₹82.89 Cr · Material ₹88.84 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
30-Jul
13-Aug
27-Aug
10-Sep
24-Sep
08-Oct
22-Oct
Lowest mandays this fortnight — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
919 works
₹56.90 Cr sanctioned
₹22.57 Cr spent (40%)
02
Plantation
1,394 works
₹43.69 Cr sanctioned
₹2.05 Cr spent (5%)
03
Construction of Check Dam/Stop Dam
531 works
₹21.81 Cr sanctioned
₹2.87 Cr spent (13%)
04
Construction of Tank
151 works
₹18.09 Cr sanctioned
₹1.10 Cr spent (6%)
05
Construction of Well
293 works
₹7.70 Cr sanctioned
₹34,338 spent (0%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹0 spent (0%)
07
Rural Housing
1,673 works
₹4.75 Cr sanctioned
₹95.73 L spent (20%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹5.97 L spent (1%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹0 spent (0%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹5.45 L spent (2%)