Monitor — Ongoing Works
Rollup last refreshed: 2026-09-20 06:52:05.620266
Works ongoing
6,191
Sanctioned (pure scheme)
₹200.39 Cr
Expenditure since inception
₹6.84 Cr
Balance cost (unspent)
₹193.55 Cr
Wage ₹104.53 Cr · Material ₹89.02 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- RAJGARH — SARANGPUR−₹99.66 L
Mandays trend
30-Jul
13-Aug
27-Aug
10-Sep
Lowest mandays this fortnight — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
866 works
₹53.25 Cr sanctioned
₹4.26 Cr spent (8%)
02
Plantation
1,403 works
₹44.10 Cr sanctioned
₹64.22 L spent (1%)
03
Construction of Check Dam/Stop Dam
519 works
₹21.68 Cr sanctioned
₹93.34 L spent (4%)
04
Construction of Tank
147 works
₹18.21 Cr sanctioned
₹26.73 L spent (1%)
05
Construction of Well
294 works
₹7.72 Cr sanctioned
₹15,309 spent (0%)
06
Constr of Compound wall
59 works
₹6.91 Cr sanctioned
₹0 spent (0%)
07
Rural Housing
1,992 works
₹5.66 Cr sanctioned
₹44.96 L spent (8%)
08
Constr of Cement Concrete Roads
51 works
₹4.50 Cr sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹27,970 spent (0%)
10
Well Recharge
86 works
₹3.54 Cr sanctioned
₹1.18 L spent (0%)