Monitor — Ongoing Works
Rollup last refreshed: 2026-10-17 07:04:51.670761
Works ongoing
6,016
Sanctioned (pure scheme)
₹202.98 Cr
Expenditure since inception
₹67.64 Cr
Balance cost (unspent)
₹135.34 Cr
Wage ₹70.60 Cr · Material ₹64.75 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
921 works
₹56.94 Cr sanctioned
₹17.52 Cr spent (31%)
02
Plantation
1,394 works
₹43.69 Cr sanctioned
₹11.02 Cr spent (25%)
03
Construction of Check Dam/Stop Dam
532 works
₹21.81 Cr sanctioned
₹9.65 Cr spent (44%)
04
Construction of Tank
151 works
₹18.09 Cr sanctioned
₹8.71 Cr spent (48%)
05
Construction of Well
293 works
₹7.70 Cr sanctioned
₹2.47 Cr spent (32%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹81.11 L spent (12%)
07
Rural Housing
1,753 works
₹4.98 Cr sanctioned
₹2.31 Cr spent (46%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹2.96 Cr spent (67%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹2.33 Cr spent (53%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹79.28 L spent (22%)