Monitor — Ongoing Works
Rollup last refreshed: 2026-10-25 07:05:11.998036
Works ongoing
5,939
Sanctioned (pure scheme)
₹202.65 Cr
Expenditure since inception
₹74.22 Cr
Balance cost (unspent)
₹128.43 Cr
Wage ₹63.72 Cr · Material ₹64.71 Cr
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
919 works
₹56.90 Cr sanctioned
₹22.86 Cr spent (40%)
02
Plantation
1,394 works
₹43.69 Cr sanctioned
₹11.34 Cr spent (26%)
03
Construction of Check Dam/Stop Dam
531 works
₹21.81 Cr sanctioned
₹10.16 Cr spent (47%)
04
Construction of Tank
151 works
₹18.09 Cr sanctioned
₹8.85 Cr spent (49%)
05
Construction of Well
293 works
₹7.70 Cr sanctioned
₹2.47 Cr spent (32%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹81.11 L spent (12%)
07
Rural Housing
1,680 works
₹4.77 Cr sanctioned
₹2.41 Cr spent (50%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹2.96 Cr spent (67%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹2.33 Cr spent (53%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹79.75 L spent (22%)