Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 06:52:44.456709
Works ongoing
6,014
Sanctioned (pure scheme)
₹202.91 Cr
Expenditure since inception
₹21.54 Cr
Balance cost (unspent)
₹181.37 Cr
Wage ₹92.54 Cr · Material ₹88.83 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
920 works
₹56.88 Cr sanctioned
₹15.11 Cr spent (27%)
02
Plantation
1,395 works
₹43.74 Cr sanctioned
₹1.69 Cr spent (4%)
03
Construction of Check Dam/Stop Dam
531 works
₹21.77 Cr sanctioned
₹2.06 Cr spent (9%)
04
Construction of Tank
151 works
₹18.09 Cr sanctioned
₹92.94 L spent (5%)
05
Construction of Well
293 works
₹7.70 Cr sanctioned
₹34,338 spent (0%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹0 spent (0%)
07
Rural Housing
1,753 works
₹4.98 Cr sanctioned
₹75.86 L spent (15%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹5.97 L spent (1%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹0 spent (0%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹4.26 L spent (1%)