Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 06:52:37.426782
Works ongoing
6,002
Sanctioned (pure scheme)
₹202.42 Cr
Expenditure since inception
₹11.55 Cr
Balance cost (unspent)
₹190.88 Cr
Wage ₹102.07 Cr · Material ₹88.81 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
917 works
₹56.52 Cr sanctioned
₹7.73 Cr spent (14%)
02
Plantation
1,395 works
₹43.74 Cr sanctioned
₹1.25 Cr spent (3%)
03
Construction of Check Dam/Stop Dam
528 works
₹21.70 Cr sanctioned
₹1.10 Cr spent (5%)
04
Construction of Tank
151 works
₹18.09 Cr sanctioned
₹53.51 L spent (3%)
05
Construction of Well
293 works
₹7.70 Cr sanctioned
₹30,252 spent (0%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹0 spent (0%)
07
Rural Housing
1,749 works
₹4.97 Cr sanctioned
₹50.53 L spent (10%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹87,472 spent (0%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹0 spent (0%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹1.29 L spent (0%)