Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
74
Sanctioned (pure scheme)
₹98.98 L
Expenditure since inception
₹65.30 L
Balance cost (unspent)
₹33.68 L
Wage ₹17.49 L · Material ₹16.19 L
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • SHAHDOL — GOHPARU−₹38.03 L
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹25.78 L sanctioned
₹21.98 L spent (85%)
02
Constr of Cement Concrete Roads
4 works
₹22.63 L sanctioned
₹15.90 L spent (70%)
03
Construction of Well
4 works
₹13.71 L sanctioned
₹8.98 L spent (66%)
04
Rural Housing
57 works
₹11.91 L sanctioned
₹7.81 L spent (66%)
05
Construction of Crematorium
3 works
₹9.18 L sanctioned
₹4.11 L spent (45%)
06
Construction of Tank
1 works
₹6.06 L sanctioned
₹1.78 L spent (29%)
07
Farm Pond
2 works
₹4.68 L sanctioned
₹3.73 L spent (80%)
08
Plantation
1 works
₹2.67 L sanctioned
₹77,845 spent (29%)
09
Bio-gas plant
1 works
₹2.38 L sanctioned
₹23,966 spent (10%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 57 11.91 7.81 4.11
66%
2 Construction of Well 4 13.71 8.98 4.73
66%
3 Constr of Cement Concrete Roads 4 22.63 15.90 6.73
70%
4 Construction of Crematorium 3 9.18 4.11 5.07
45%
5 Farm Pond 2 4.68 3.73 0.95
80%
6 Plantation 1 2.67 0.78 1.89
29%
7 Construction of Tank 1 6.06 1.78 4.28
29%
8 Bio-gas plant 1 2.38 0.24 2.14
10%
9 Construction of Road and Culvert 1 25.78 21.98 3.80
85%
Total 74 98.98 65.30 33.68
All 9 rows (zero-value rows hidden) ⇩ Export to Excel