MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-04 07:04:00.535302
to
Reset filters
Works ongoing
20,328
Sanctioned (pure scheme)
₹134.42 Cr
Expenditure since inception
₹55.47 Cr
Balance cost (unspent)
₹78.95 Cr
Wage ₹57.86 Cr · Material ₹21.09 Cr
Expenditure trend
₹27.93 Cr
This Week
₹23.43 Cr
Last Week
▲ 19.2% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Mandays trend
11,04,706
This Week
11,32,881
Last Week
▼ 2.5%
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
18,265 works
₹49.20 Cr sanctioned
₹18.05 Cr spent (37%)
02
Plantation
526 works
₹13.22 Cr sanctioned
₹2.30 Cr spent (17%)
03
Construction of Tank
162 works
₹13.10 Cr sanctioned
₹8.17 Cr spent (62%)
04
Construction of Road and Culvert
83 works
₹12.07 Cr sanctioned
₹7.45 Cr spent (62%)
05
Farm Pond
303 works
₹9.39 Cr sanctioned
₹2.76 Cr spent (29%)
06
Construction of Well
246 works
₹7.17 Cr sanctioned
₹3.35 Cr spent (47%)
07
Constr of Cement Concrete Roads
252 works
₹7.02 Cr sanctioned
₹3.57 Cr spent (51%)
08
Construction of Check Dam/Stop Dam
76 works
₹3.66 Cr sanctioned
₹1.49 Cr spent (41%)
09
Repair & maint of Pond/ Tank
40 works
₹3.24 Cr sanctioned
₹2.45 Cr spent (76%)
10
Cattle Shed
8 works
₹2.73 Cr sanctioned
₹1.23 Cr spent (45%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 18,265 49.20 18.05 31.15
37%
2 Plantation 526 13.22 2.30 10.92
17%
3 Farm Pond 303 9.39 2.76 6.62
29%
4 Constr of Cement Concrete Roads 252 7.02 3.57 3.45
51%
5 Construction of Well 246 7.17 3.35 3.82
47%
6 Construction of Tank 162 13.10 8.17 4.93
62%
7 Construction of Road and Culvert 83 12.07 7.45 4.62
62%
8 Construction of Check Dam/Stop Dam 76 3.66 1.49 2.17
41%
9 Construction of Crematorium 75 1.79 1.22 0.58
68%
10 Repair & maint of Pond/ Tank 40 3.24 2.45 0.79
76%
11 Solid and Liquid Waste Management 37 0.20 0.09 0.11
46%
12 Land Development 24 1.94 0.54 1.41
28%
13 Constr of GP Bhawan 23 1.30 0.47 0.83
36%
14 Well Recharge 23 0.84 0.12 0.72
14%
15 Construction of Trench 21 1.58 0.72 0.86
46%
16 Community Sanitary Complex 20 0.16 0.08 0.08
48%
17 Constr of Aganwadi 17 0.38 0.23 0.15
61%
18 Construction of NADEP/Vermi Compost Pit 17 0.13 0.05 0.08
41%
19 Construction of Toilets 14 0.05 0.03 0.02
54%
20 Construction of Percolation Tank 13 0.30 0.07 0.23
22%
21 Construction of Recharge Pits 11 0.13 0.01 0.12
9%
22 Construction of Play field 10 0.24 0.10 0.15
39%
23 Grass Land Development 9 0.72 0.04 0.67
6%
24 Constr of Compound wall 9 0.17 0.12 0.05
73%
25 Cattle Shed 8 2.73 1.23 1.50
45%
26 Construction of Bund 8 0.33 0.05 0.28
16%
27 Nursery Development 7 2.01 0.17 1.85
8%
28 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 5 0.21 0.07 0.13
35%
29 Culvert 5 0.03 0.01 0.02
38%
30 Terracing 3 0.26 0.20 0.07
75%
31 Underground Dyke for Ground Water Recharge 3 0.17 0.09 0.09
51%
32 Constr of Gabion 3 0.44 0.16 0.29
35%
33 Construction of Other Community Building/Assets 2 0.06 0.00 0.05
8%
34 Bio-Fertilizer 1 0.03 0.00 0.03
2%
35 Works for Flood Control and Protection 1 0.00 0.00 0.00
1%
36 Constr of Food Grain storage 1 0.02 0.00 0.02
9%
37 Bio-gas plant 1 0.02 0.00 0.02
10%
38 Repair & maint of Road 1 0.01 0.00 0.01
27%
39 Other Works 1 0.03 0.00 0.03
3%
40 Construction of Canal 1 0.01 0.00 0.00
24%
41 Repair & Maint of Community infrastructure 1 0.04 0.01 0.03
29%
Total 20,328 134.42 55.47 78.95
All 41 rows (zero-value rows hidden) ⇩ Export to Excel