Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
22,924
Sanctioned (pure scheme)
₹134.88 Cr
Expenditure since inception
₹54.34 Cr
Balance cost (unspent)
₹80.54 Cr
Wage ₹59.66 Cr · Material ₹20.89 Cr
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
- KHANDWA — PANDHANA−₹93.68 L
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
20,839 works
₹48.73 Cr sanctioned
₹15.89 Cr spent (33%)
02
Plantation
533 works
₹13.30 Cr sanctioned
₹2.22 Cr spent (17%)
03
Construction of Tank
166 works
₹13.19 Cr sanctioned
₹8.14 Cr spent (62%)
04
Construction of Road and Culvert
79 works
₹11.28 Cr sanctioned
₹7.24 Cr spent (64%)
05
Farm Pond
304 works
₹9.41 Cr sanctioned
₹2.78 Cr spent (29%)
06
Construction of Well
248 works
₹7.23 Cr sanctioned
₹3.35 Cr spent (46%)
07
Constr of Cement Concrete Roads
252 works
₹7.02 Cr sanctioned
₹3.54 Cr spent (50%)
08
Cattle Shed
12 works
₹4.04 Cr sanctioned
₹2.49 Cr spent (62%)
09
Construction of Check Dam/Stop Dam
78 works
₹3.69 Cr sanctioned
₹1.48 Cr spent (40%)
10
Repair & maint of Pond/ Tank
40 works
₹3.24 Cr sanctioned
₹2.39 Cr spent (74%)