Works ongoing
7,361
Sanctioned (pure scheme)
₹242.66 Cr
Expenditure since inception
₹1.92 Cr
Balance cost (unspent)
₹240.73 Cr
Wage ₹131.33 Cr · Material ₹109.41 Cr
Expenditure trend
▲ 16.2% vs last fortnight
30-Jul
13-Aug
27-Aug
10-Sep
Slowest spending this fortnight — worth a look
- RAJGARH — SARANGPUR−₹80.73 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
295 works
₹74.88 Cr sanctioned
₹54.22 L spent (1%)
02
Plantation
3,534 works
₹63.91 Cr sanctioned
₹96.10 L spent (2%)
03
Construction of Check Dam/Stop Dam
237 works
₹38.64 Cr sanctioned
₹13.28 L spent (0%)
04
Construction of Well
992 works
₹29.85 Cr sanctioned
₹5.61 L spent (0%)
05
Constr of Cement Concrete Roads
145 works
₹7.18 Cr sanctioned
₹1.22 L spent (0%)
06
Construction of Percolation Tank
62 works
₹6.89 Cr sanctioned
₹6.12 L spent (1%)
07
Rural Housing
1,435 works
₹3.87 Cr sanctioned
₹10.39 L spent (3%)
08
Farm Pond
150 works
₹3.77 Cr sanctioned
₹2.58 L spent (1%)
09
Construction of Road and Culvert
19 works
₹2.38 Cr sanctioned
₹0 spent (0%)
10
Well Recharge
106 works
₹2.25 Cr sanctioned
₹11,394 spent (0%)