Monitor — Ongoing Works
Rollup last refreshed: 2026-10-08 11:14:22.304268
Works ongoing
6,847
Sanctioned (pure scheme)
₹233.19 Cr
Expenditure since inception
₹2.37 Cr
Balance cost (unspent)
₹230.82 Cr
Wage ₹125.28 Cr · Material ₹105.54 Cr
Expenditure trend
Slowest spending this qtr — worth a look
- DINDORI — DINDORI−₹17.53 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
- KHARGONE — BHAGVANPURA-1,577
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
285 works
₹73.33 Cr sanctioned
₹55.38 L spent (1%)
02
Plantation
3,334 works
₹60.67 Cr sanctioned
₹1.20 Cr spent (2%)
03
Construction of Check Dam/Stop Dam
223 works
₹37.92 Cr sanctioned
₹12.04 L spent (0%)
04
Construction of Well
943 works
₹28.45 Cr sanctioned
₹8.77 L spent (0%)
05
Constr of Cement Concrete Roads
144 works
₹7.14 Cr sanctioned
₹5.57 L spent (1%)
06
Construction of Percolation Tank
58 works
₹6.53 Cr sanctioned
₹6.04 L spent (1%)
07
Farm Pond
136 works
₹3.44 Cr sanctioned
₹2.53 L spent (1%)
08
Rural Housing
1,256 works
₹3.39 Cr sanctioned
₹13.71 L spent (4%)
09
Well Recharge
93 works
₹1.97 Cr sanctioned
₹35,227 spent (0%)
10
Construction of Road and Culvert
17 works
₹1.95 Cr sanctioned
₹2.00 L spent (1%)