Monitor — Ongoing Works
Rollup last refreshed: 2026-09-06 07:04:10.165253
Works ongoing
7,833
Sanctioned (pure scheme)
₹250.75 Cr
Expenditure since inception
₹132.42 Cr
Balance cost (unspent)
₹118.33 Cr
Wage ₹73.74 Cr · Material ₹44.59 Cr
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
306 works
₹76.11 Cr sanctioned
₹49.93 Cr spent (66%)
02
Plantation
3,695 works
₹66.35 Cr sanctioned
₹18.40 Cr spent (28%)
03
Construction of Check Dam/Stop Dam
250 works
₹39.31 Cr sanctioned
₹29.54 Cr spent (75%)
04
Construction of Well
1,039 works
₹31.21 Cr sanctioned
₹14.74 Cr spent (47%)
05
Construction of Percolation Tank
65 works
₹7.39 Cr sanctioned
₹4.68 Cr spent (63%)
06
Constr of Cement Concrete Roads
147 works
₹7.20 Cr sanctioned
₹5.58 Cr spent (77%)
07
Farm Pond
177 works
₹4.75 Cr sanctioned
₹1.32 Cr spent (28%)
08
Rural Housing
1,619 works
₹4.37 Cr sanctioned
₹1.97 Cr spent (45%)
09
Construction of Road and Culvert
20 works
₹2.52 Cr sanctioned
₹1.83 Cr spent (73%)
10
Well Recharge
116 works
₹2.30 Cr sanctioned
₹65.14 L spent (28%)