Monitor — Ongoing Works
Rollup last refreshed: 2026-09-26 07:03:36.929547
Works ongoing
95
Sanctioned (pure scheme)
₹1.22 Cr
Expenditure since inception
₹47.71 L
Balance cost (unspent)
₹74.42 L
Wage ₹36.15 L · Material ₹38.27 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
6 works
₹45.22 L sanctioned
₹21.21 L spent (47%)
02
Construction of Tank
1 works
₹31.36 L sanctioned
₹8.75 L spent (28%)
03
Rural Housing
78 works
₹22.23 L sanctioned
₹7.24 L spent (33%)
04
Plantation
4 works
₹7.60 L sanctioned
₹3.00 L spent (39%)
05
Community Sanitary Complex
1 works
₹5.46 L sanctioned
₹1.22 L spent (22%)
06
Construction of Bund
1 works
₹3.18 L sanctioned
₹1.88 L spent (59%)
07
Construction of Well
1 works
₹2.73 L sanctioned
₹84,920 spent (31%)
08
Land Development
1 works
₹2.34 L sanctioned
₹1.57 L spent (67%)
09
Constr of Cement Concrete Roads
1 works
₹2.00 L sanctioned
₹1.98 L spent (99%)
10
Farm Pond
1 works
₹0 sanctioned
₹167 spent (0%)