Rollup last refreshed: 2026-09-06 07:04:10.165253
Works ongoing
3,524
Sanctioned (pure scheme)
₹74.63 Cr
Expenditure since inception
₹26.92 Cr
Balance cost (unspent)
₹47.71 Cr
Wage ₹24.21 Cr · Material ₹23.50 Cr
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
614 works
₹16.73 Cr sanctioned
₹4.57 Cr spent (27%)
02
Construction of Tank
57 works
₹7.38 Cr sanctioned
₹4.16 Cr spent (56%)
03
Construction of Well
145 works
₹4.62 Cr sanctioned
₹1.84 Cr spent (40%)
04
Constr of Cement Concrete Roads
111 works
₹4.45 Cr sanctioned
₹77.22 L spent (17%)
05
Rural Housing
1,558 works
₹4.21 Cr sanctioned
₹1.73 Cr spent (41%)
06
Construction of Trench
52 works
₹4.13 Cr sanctioned
₹1.14 Cr spent (28%)
07
Repair & maint of Pond/ Tank
59 works
₹4.09 Cr sanctioned
₹1.98 Cr spent (48%)
08
Construction of Bund
79 works
₹3.65 Cr sanctioned
₹1.38 Cr spent (38%)
09
Construction of Check Dam/Stop Dam
27 works
₹3.15 Cr sanctioned
₹1.83 Cr spent (58%)
10
Construction of Road and Culvert
28 works
₹2.59 Cr sanctioned
₹1.55 Cr spent (60%)