Monitor — Ongoing Works
Rollup last refreshed: 2026-10-12 07:04:13.185207
Works ongoing
54
Sanctioned (pure scheme)
₹51.80 L
Expenditure since inception
₹13.27 L
Balance cost (unspent)
₹38.53 L
Wage ₹25.86 L · Material ₹12.67 L
Expenditure trend
Slowest spending this qtr — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Land Development
1 works
₹14.94 L sanctioned
₹5.83 L spent (39%)
02
Construction of Tank
1 works
₹14.71 L sanctioned
₹204 spent (0%)
03
Rural Housing
50 works
₹13.50 L sanctioned
₹1.91 L spent (14%)
04
Construction of Well
2 works
₹8.65 L sanctioned
₹5.53 L spent (64%)
05
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)