MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-21 06:52:32.583578
to
Reset filters
Works ongoing
43
Sanctioned (pure scheme)
₹56.65 L
Expenditure since inception
₹37,527
Balance cost (unspent)
₹56.28 L
Wage ₹33.81 L · Material ₹22.46 L
Expenditure trend
₹3.01 Cr
This Week
₹34.28 Cr
Last Week
▼ 91.2% vs last week
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
  • DEWAS — TONK KHURD−₹6,000
Mandays trend
1,06,187
This Week
11,30,691
Last Week
▼ 90.6%
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
  • BALAGHAT — BAIHAR0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Repair & maint of Pond/ Tank
2 works
₹19.95 L sanctioned
₹0 spent (0%)
02
Plantation
6 works
₹9.07 L sanctioned
₹0 spent (0%)
03
Rural Housing
20 works
₹5.40 L sanctioned
₹37,527 spent (7%)
04
Construction of Tank
1 works
₹4.83 L sanctioned
₹0 spent (0%)
05
Farm Pond
4 works
₹4.81 L sanctioned
₹0 spent (0%)
06
Construction of Percolation Tank
1 works
₹3.39 L sanctioned
₹0 spent (0%)
07
Constr of Aganwadi
1 works
₹3.31 L sanctioned
₹0 spent (0%)
08
Terracing
1 works
₹2.48 L sanctioned
₹0 spent (0%)
09
Cattle Shed
2 works
₹1.28 L sanctioned
₹0 spent (0%)
10
Construction of Toilets
1 works
₹75,000 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 20 5.40 0.38 5.02
7%
2 Plantation 6 9.07 0.00 9.07
0%
3 Farm Pond 4 4.81 0.00 4.81
0%
4 Repair & maint of Pond/ Tank 2 19.95 0.00 19.95
0%
5 Cattle Shed 2 1.28 0.00 1.28
0%
6 Construction of Recharge Pits 1 0.14 0.00 0.14
0%
7 Construction of Tank 1 4.83 0.00 4.83
0%
8 Construction of Toilets 1 0.75 0.00 0.75
0%
9 Terracing 1 2.48 0.00 2.48
0%
10 Well Recharge 1 0.26 0.00 0.26
0%
11 Constr of Aganwadi 1 3.31 0.00 3.31
0%
12 Constr of Cement Concrete Roads 1 0.35 0.00 0.35
0%
13 Construction of Bund 1 0.63 0.00 0.63
0%
14 Construction of Percolation Tank 1 3.39 0.00 3.39
0%
Total 43 56.65 0.38 56.28