Monitor — Ongoing Works

Rollup last refreshed: 2026-10-01 08:49:21.894441
to
Reset filters
Works ongoing
47
Sanctioned (pure scheme)
₹1.25 Cr
Expenditure since inception
₹67.05 L
Balance cost (unspent)
₹57.87 L
Wage ₹35.46 L · Material ₹22.41 L
Expenditure trend
₹17.46 Cr
This Week
₹23.43 Cr
Last Week
▼ 25.5% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
  • REWA — GANGEV−₹63.02 L
Mandays trend
1,72,615
This Month
49,10,850
Last Month
▼ 96.5%
Jun-26
Jul-26
Aug-26
Sep-26
Oct-26
Lowest mandays this month — worth a look
  • DHAR — KUKSHI-17,331

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Constr of GP Bhawan
1 works
₹38.04 L sanctioned
₹34.95 L spent (92%)
02
Construction of Road and Culvert
1 works
₹17.37 L sanctioned
₹13.43 L spent (77%)
03
Construction of Trench
1 works
₹14.68 L sanctioned
₹3.43 L spent (23%)
04
Construction of Bund
1 works
₹14.23 L sanctioned
₹3.86 L spent (27%)
05
Plantation
3 works
₹10.81 L sanctioned
₹47,736 spent (4%)
06
Rural Housing
35 works
₹9.45 L sanctioned
₹3.93 L spent (42%)
07
Land Development
1 works
₹7.92 L sanctioned
₹1.42 L spent (18%)
08
Well Recharge
1 works
₹5.36 L sanctioned
₹2.89 L spent (54%)
09
Construction of Tank
1 works
₹5.36 L sanctioned
₹98,550 spent (18%)
10
Solid and Liquid Waste Management
1 works
₹99,000 sanctioned
₹98,307 spent (99%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 35 9.45 3.93 5.52
42%
2 Plantation 3 10.81 0.48 10.33
4%
3 Land Development 1 7.92 1.42 6.51
18%
4 Construction of Bund 1 14.23 3.86 10.37
27%
5 Construction of Trench 1 14.68 3.43 11.25
23%
6 Constr of Cement Concrete Roads 1 0.71 0.70 0.01
99%
7 Constr of GP Bhawan 1 38.04 34.95 3.10
92%
8 Solid and Liquid Waste Management 1 0.99 0.98 0.01
99%
9 Construction of Road and Culvert 1 17.37 13.43 3.93
77%
10 Well Recharge 1 5.36 2.89 2.47
54%
11 Construction of Tank 1 5.36 0.99 4.37
18%
Total 47 124.91 67.05 57.87
All 11 rows (zero-value rows hidden) ⇩ Export to Excel