| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Rural Housing | 11 | 2.97 | 0.30 | 2.67 | 10% |
| 2 | Works for Flood Control and Protection | 9 | 63.53 | 45.14 | 18.39 | 71% |
| 3 | Plantation | 6 | 16.00 | 0.14 | 15.86 | 1% |
| 4 | Construction of Crematorium | 2 | 7.11 | 1.05 | 6.06 | 15% |
| 5 | Constr of GP Bhawan | 1 | 7.00 | 5.56 | 1.44 | 80% |
| 6 | Construction of Road and Culvert | 1 | 19.38 | 17.05 | 2.33 | 88% |
| 7 | Constr of Aganwadi | 1 | 5.00 | 0.35 | 4.65 | 7% |
| 8 | Constr of Cement Concrete Roads | 1 | 0.47 | 0.27 | 0.19 | 59% |
| 9 | Constr of Compound wall | 1 | 5.88 | 4.33 | 1.55 | 74% |
| 10 | Farm Pond | 1 | 1.50 | 0.96 | 0.54 | 64% |
| Total | 34 | 128.84 | 75.15 | 53.69 |