| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Farm Pond | 6 | 6.10 | 0.15 | 5.95 | 3% |
| 2 | Rural Housing | 4 | 1.08 | 0.86 | 0.22 | 79% |
| 3 | Constr of Cement Concrete Roads | 3 | 2.73 | 0.44 | 2.29 | 16% |
| 4 | Works for Flood Control and Protection | 2 | 1.83 | 1.80 | 0.03 | 99% |
| 5 | Constr of Aganwadi | 1 | 1.80 | 1.76 | 0.04 | 98% |
| 6 | Construction of Tank | 1 | 7.13 | 0.22 | 6.91 | 3% |
| 7 | Plantation | 1 | 2.93 | 0.03 | 2.90 | 1% |
| 8 | Construction of Bund | 1 | 14.25 | 0.01 | 14.24 | 0% |
| 9 | Solid and Liquid Waste Management | 1 | 0.09 | 0.01 | 0.08 | 13% |
| 10 | Repair & maint of Pond/ Tank | 1 | 10.97 | 0.02 | 10.95 | 0% |
| Total | 21 | 48.91 | 5.31 | 43.61 |