Monitor — Ongoing Works

Rollup last refreshed: 2026-09-18 07:04:14.05263
to
Reset filters
Works ongoing
19
Sanctioned (pure scheme)
₹1.74 Cr
Expenditure since inception
₹58.20 L
Balance cost (unspent)
₹1.16 Cr
Wage ₹15.06 L · Material ₹1.01 Cr
Expenditure trend
₹23.77 Cr
This Week
₹39.19 Cr
Last Week
▼ 39.4% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • RAJGARH — SARANGPUR−₹1.04 Cr
Mandays trend
7,49,397
This Week
10,41,857
Last Week
▼ 28.1%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-16,931

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Constr of GP Bhawan
5 works
₹63.91 L sanctioned
₹19.86 L spent (31%)
02
Constr of Cement Concrete Roads
3 works
₹44.88 L sanctioned
₹4.64 L spent (10%)
03
Construction of Bund
1 works
₹14.78 L sanctioned
₹13.55 L spent (92%)
04
Construction of Road and Culvert
1 works
₹14.73 L sanctioned
₹2.88 L spent (20%)
05
Terracing
1 works
₹14.36 L sanctioned
₹14.18 L spent (99%)
06
Works for Flood Control and Protection
1 works
₹12.00 L sanctioned
₹1.26 L spent (10%)
07
Plantation
3 works
₹8.19 L sanctioned
₹1.35 L spent (17%)
08
Rural Housing
3 works
₹81,000 sanctioned
₹45,936 spent (57%)
09
Construction of NADEP/Vermi Compost Pit
1 works
₹57,000 sanctioned
₹2,316 spent (4%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Constr of GP Bhawan 5 63.91 19.86 44.05
31%
2 Rural Housing 3 0.81 0.46 0.35
57%
3 Plantation 3 8.19 1.35 6.83
17%
4 Constr of Cement Concrete Roads 3 44.88 4.64 40.24
10%
5 Terracing 1 14.36 14.18 0.18
99%
6 Works for Flood Control and Protection 1 12.00 1.26 10.75
11%
7 Construction of NADEP/Vermi Compost Pit 1 0.57 0.02 0.55
4%
8 Construction of Bund 1 14.78 13.55 1.23
92%
9 Construction of Road and Culvert 1 14.73 2.88 11.85
20%
Total 19 174.23 58.20 116.03
All 9 rows (zero-value rows hidden) ⇩ Export to Excel