Monitor — Ongoing Works
Rollup last refreshed: 2026-08-05 08:30:05.836701
Works ongoing
21
Sanctioned (pure scheme)
₹1.69 Cr
Expenditure since inception
₹76.78 L
Balance cost (unspent)
₹91.91 L
Wage ₹48.70 L · Material ₹43.21 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
2 works
₹49.39 L sanctioned
₹40.26 L spent (82%)
02
Plantation
6 works
₹45.25 L sanctioned
₹3.91 L spent (9%)
03
Works for Flood Control and Protection
10 works
₹39.69 L sanctioned
₹17.79 L spent (45%)
04
Construction of Check Dam/Stop Dam
1 works
₹14.85 L sanctioned
₹3.04 L spent (20%)
05
Construction of Tank
1 works
₹12.02 L sanctioned
₹4.37 L spent (36%)
06
Constr of GP Bhawan
1 works
₹7.50 L sanctioned
₹7.41 L spent (99%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Embankment
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)